What Old Town Beaverton's Hall Boulevard Rebuild Changes, Block by Block

What would the Downtown Loop actually feel like underfoot? Beaverton has talked about the Loop since the City Council adopted the Downtown Loop Complete Street Concept Plan on May 16, 2023. Until now it has existed as drawings, grant applications and a route on a map. The first real answer covers two blocks: SW Hall Boulevard between SW 1st and SW 3rd streets in Old Town.

The city has finished designing that stretch. Beaverton Beat reported on Oct. 29 that the overhaul carries a $12.2 million price tag and is "the first built piece of the long-planned Downtown Loop." The bigger sections of the Loop are still in planning, so for the next few years these two blocks will be the only place to see the full idea built: a downtown street where walking, biking and buses get room equal to cars.

Why Hall Comes First

The Loop is meant to be one connected downtown route along Hall Boulevard, Watson Avenue and 5th Street that puts walking, biking and transit first. The city describes its purpose as connecting Old Town and Beaverton Central along Hall and Watson and linking the civic, cultural and economic destinations between them.

The 1st-to-3rd segment started as a federal demonstration project, funded with Community Project Funding secured through Rep. Suzanne Bonamici's office and matched by the Beaverton Urban Redevelopment Agency, known as BURA. Beaverton Beat breaks the cost down as roughly $5.6 million in federal money and $6.6 million in local BURA funds, which includes a $4.8 million local overmatch. ODOT is the city's delivery partner. It hired the design consultant and will select the construction contractor, while the city ran community engagement and design review.

The intersection at the center of the project was chosen with data behind it. ODOT crash data identified the crossing at Hall and 2nd Street as the spot in the project area most in need of safety improvements. That crossing explains most of the design.

The Street, Block by Block

Both blocks get a complete roadway reconstruction. Because each block solves a different space problem, the changes are easiest to follow one block at a time.

SW 1st to SW 2nd

Travel lanes and the parking lane narrow to make room for a wider sidewalk on the west side and a new bike lane. The bike lane is protected and sits at pavement level. Parking stays on this block, in a slimmer lane.

The Corner at Hall and 2nd

This corner changes the most:

  • A pedestrian-activated flashing warning system at the crossing ODOT's data flagged.
  • A new TriMet stop at the northeast corner, where buses will stop in their travel lane. The stop sits within the bike lane and uses a shared bike-and-pedestrian layout that TriMet has approved and used on earlier projects.
  • Raised concrete intersections at sidewalk level replace the striped crossings at pavement level, and corners extend farther into the street to shorten the walk across and slow vehicles.

SW 2nd to SW 3rd

East-side parking goes away on this block so both sidewalks can widen and the bike lane can run through. West-side parking stays.

Along both blocks, two driveways on Hall will close to reduce conflict points with people walking and biking. Parking lots keep full access through their other existing driveways, and the city's agenda bill states that affected property owners have been supportive. New streetlights, benches, bike racks and street trees complete the design, with fixtures chosen to match existing Old Town styles. No right-of-way purchases are needed for this phase.

The Calendar the Work Follows

Construction will run in seasons, and that matters most for anyone who uses Old Town regularly. The schedule:

  1. July 2026: Design work wrapped up.
  2. Oct. 27, 2026: The completed design and a construction preview went to the BURA board.
  3. December 2026: ODOT is expected to advertise the project for bids.
  4. Early 2027: Construction activities are expected to begin.
  5. March to October, 2027 and 2028: The heaviest work is expected in these two windows.

So the downtown many people know now stays largely as it is through this winter. The two main disruption windows are the warm-weather months of the next two years.

The city has said downtown will remain open during the work. A preliminary traffic control plan sets out how vehicles and pedestrians will get through, and contract specifications will limit driveway, sidewalk and street closures and require timely notice to affected businesses. City staff met with adjacent property and business owners in spring 2026, and an April 2026 constructibility workshop covered construction sequencing and business access. The project team also plans to share the finished design with the Beaverton Downtown Association and the Central Beaverton Neighborhood Association Committee.

The Rest of the Loop, Piece by Piece

These two blocks will serve as the Loop's working sample for a while, because the rest of the Loop is moving on its own timeline.

The next major piece is the Promenade, the Hall-and-Watson section between Millikan Way and 1st Street. Its planning work aims for 60% design on the Promenade, including a railroad Quiet Zone, and 30% design for the wider Loop. Beaverton Beat reports that design work on the rest of the Loop, funded by a federal RAISE planning grant, is expected to begin in 2027. Building the Promenade will take more money. The city applied for federal BUILD grants in 2025 and 2026 without receiving an award. Washington County's Major Streets Transportation Improvement Program includes $13 million for the Watson segment, and the city and county are working out whether to spend it on construction, use it as a local match for a future grant, or both.

A separate downtown project shares the Loop's goal of making room for people on foot. The 1st Street Dining Commons on SW 1st between Washington and Watson is headed toward a permanent, flexible design. Plans include sidewalks brought up to code, street trees, streetlamps and infrastructure that makes the street easy to close as a plaza. The October BURA update notes that the Beaverton Downtown Association programmed the space all summer and drew thousands of visitors downtown. Taken together, Hall shows what the Loop's streets could look like, and 1st Street shows what its gathering spaces could look like.

Old Town This Winter, Before the Crews Arrive

The weeks around the bid announcement are a normal season downtown, and a few fixtures sit just beyond the construction zone.

  • Beaverton Farmers Market sets up across from the Beaverton City Library on SW Hall between 3rd and 5th, one block past the end of the rebuild. Its 2026 Saturday season runs through Nov. 21. Earlier this year, its Winter Market 2026 ran Saturdays in February and March from 10 a.m. to 1:30 p.m. The market's site is where the next season's dates will be posted.
  • Fiesta on First takes place at the 1st Street Dining Commons on the last Tuesday of each month, 6 to 8 p.m., according to the Downtown Beaverton Association.
  • The Reser is in its fifth-anniversary season. The Curio, a gallery collaboration with the Beaverton Arts Market that features and sells work by Northwest artists and craftspeople, runs Nov. 6 through Jan. 10, 2027. A Mexican Christmas folklórico and mariachi performance is on Nov. 28, and Kids' New Year's Eve is on Dec. 31, per the Reser's season announcement.
  • Fly Chai, a masala chai house at 12520 SW Farmington Road, was profiled by Beaverton Beat for its Assam tea and jaggery chai, served in three blends with adjustable sweetness and spice.

For more on how downtown's event calendar has grown, see our look at Downtown Beaverton's first ticketed food festival. Our Beaverton neighborhood guide covers the city beyond Old Town.

When ODOT opens bidding in December, the schedule for Hall between 1st and 3rd will become firmer. The first full season of work is expected to start in March 2027, with a second season in 2028.

If you own property near Old Town and want to talk through how a two-season street project might affect your timing, Matt Booth Winback is glad to walk through it with you. Let's Connect.

Work With Matt

With a background in real estate law and over a decade of industry experience, he provides knowledgeable guidance and strong advocacy throughout every transaction. Combining deep local market expertise with a detail-oriented approach, he helps buyers and sellers navigate the process with confidence, clarity, and peace of mind.